The United States Court of Appeals (Federal Circuit) (“Appellate Court”) addressed in an August 26th Opinion a dispute regarding certain costs associated with a Federal Highway Administration (“FHA”) road design and reconstruction project. See Kiewit Infrastructure West Co. v. United States, 2020 WL 5032464. The issue involved a contractor’s request for additional payment for the increased cost of purchasing wetland mitigation credits....
By:
Mitchell, Williams, Selig, Gates & Woodyard,
Source Url: https://www.jdsupra.com/legalnews/wetland-mitigation-credits-government-83865/
Related
Leveraged buyout high yield bond and leveraged loan issuance fell in Q3 2020 as a lack of buyout dea...
Read More >
Just as no human being is naturally immune to the COVID-19 virus, no industry is immune to its econo...
Read More >
In the world of M&A and private equity deals, buyer-side representation and warranties insurance (RW...
Read More >
Every facet of the construction industry has been impacted by COVID-19. Commercial and residential ...
Read More >
Almost a decade into the current bull market, many economic prognosticators are warning of a coming ...
Read More >
In the first quarter of 2020, no sector was able to avoid the declining interest in M&A caused b...
Read More >