Court of Federal Claims Provides Guidance on Recovery of Unabsorbed Overhead and the Christian Doctrine

In Kudsk Construction Inc. v. The United States, No. 18-1032C (August 30, 2019), the Court of Federal Claims addressed damages in the context of a delayed notice to proceed and addressed the Christian doctrine in the context of recent federal...
By: Davis Wright Tremaine LLP
Source Url: https://www.jdsupra.com/legalnews/court-of-federal-claims-provides-37855/

Related

[Webinar] The Dangers of Housing Independent Contractors (ICs) in Your HRIS - August 14th, 3:00pm ET

In this one-hour webcast, Wendy will help your understanding of how to best manage Independent Contr...

Read More >

Court Reverses Award of COBRA Penalties

The Sixth Circuit Court of Appeals reversed a district court’s decision to award statutory penaltie...

Read More >

Phase 1 Construction Guidelines: Guidance for Real Estate Developers in New York City

On Monday New York City entered Phase 1 of re-opening. Phase 1 guidance provides specific guidelines...

Read More >

FTC and DOJ ‘Temporarily’ Suspend Early Termination Grants; No Clear End to Suspension Identified

The DOJ and FTC have suspended early termination (i.e., early clearance) for filings made under the ...

Read More >

AB 5 Returned To The CA Senate

The California worker classification bill, Assembly Bill 5 (AB 5), advanced closer to passage just p...

Read More >

It’s a New Day at the NLRB: Four Recent Decisions Leap Back to More Employer-Friendly Times

Depending on whom you ask, labor law during the Obama administration was “the best of times, the wo...

Read More >