The English Court of Appeal applies 'but for' test to "Force Majeure Clause" – FIDIC’s "Exceptional Events" now under threat?

International Construction Arbitration has received a shock. Consistent with the leading textbooks, a party seeking to rely on force majeure in a construction contract did not have to show that ‘but for’ the force majeure event it would have...
By: Akin Gump Strauss Hauer & Feld LLP
Source Url: https://www.jdsupra.com/legalnews/the-english-court-of-appeal-applies-but-91995/

Related

Beltway Buzz - February 2020 #3

EEOC Clarifies EEO-1 Requirements. The Equal Employment Opportunity Commission (EEOC) confirmed that...

Read More >

Alert: D.C. Circuit Casts Doubt on FCC’s Authority to Impose Merger Conditions

In a recent decision reversing FCC-imposed conditions on Charter Communications’ 2016 acquisition o...

Read More >

New Year, New Restrictions on Non-Compete Agreements

States across the country continue to enact legislation limiting the use of non-compete agreements. ...

Read More >

The CCPA: Employee Data Requirements May Be Delayed, But Do Not Appear to be Going Away

Action is currently underway to amend the California Consumer Privacy Act (“CCPA”) to provide empl...

Read More >

New Jersey Expands Information Required In Wage Statements Of Deductions

New Jersey has amended its Wage Payment Law (WPL) to require employers with at least 10 employees to...

Read More >

New Int'l Arbitration Study Offers Construction Dispute Insight

On Nov. 21, the Queen Mary University of London School of International Arbitration, in partnership ...

Read More >