New York Court Holds Contractor’s Failure to Timely Pass Through Subcontractor Delay Claim to the Owner Constitutes Breach of the Covenant of Good Faith and Fair Dealing

Rad and D’Aprile, Inc. v. Arnell Construction Corp, No. 502464/14, 2019 BL 131606 (NY. Sup. Ct. April 3, 2019) - In June of 2001, Arnell Construction Corp. (“Arnell”) entered into a prime contract to build two sanitation garages in Brooklyn for the...
By: Pepper Hamilton LLP
Source Url: https://www.jdsupra.com/legalnews/new-york-court-holds-contractor-s-29389/

Related

[Video] Trekking Through Compliance-Episode 50 – Patterns of Force

In this episode of Trekking Through Compliance, we consider the episode Patterns of Force which aire...

Read More >

Web Exclusive: Planning For DOL’s Overtime Rules In A Tough Labor Climate

The U.S. Department of Labor recently announced proposed regulations on overtime that would render m...

Read More >

Illinois Governor Issues Shelter-in-Place Order in Response to the Coronavirus that Spares the Construction Industry

Illinois Governor J.B. Pritzker issued a shelter-in-place Executive Order on March 20, 2020, the lat...

Read More >

K&L Gates Triage: Health Care Provider v. Payor Disputes Simplified: Getting Around ERISA Preemption

In this week’s episode, Gary Qualls discusses the recent Louisiana federal district court decision ...

Read More >

Utah Legislature Contemplating Sick Leave For Immediate Family

The Utah Legislature is in session again, and it’s likely that there will be changes in the Utah em...

Read More >

MVA Monitor - May 2019 #2

It was another fairly quiet week at the General Assembly. Several House committees advanced bills th...

Read More >