Massachusetts Court Clarifies Statute of Repose Trigger for Multi-Phase Construction Projects

In D’Allesandro v. Lennar Hingham Holdings, LLC, C.A. No. 17-cv-12567-IT, 2019 U.S. Dist. LEXIS 185874, the United States District Court for the District of Massachusetts recently discussed a case against a general contractor and its related...
By: White and Williams LLP
Source Url: https://www.jdsupra.com/legalnews/massachusetts-court-clarifies-statute-34337/

Related

No Way Around It: The Need for Federal "Permission and Assistance" Can Preempt a State Tort Duty

In the simplest case for federal preemption, federal law prohibits conduct that a state tort duty wo...

Read More >

Don’t Assume That Closely Related Agreements Will Be Interpreted As One Contract

In some transactions, such as those involving the acquisition of a business, the deal may be documen...

Read More >

Seyfarth Policy Matters Newsletter - January 2020 #2

With the eyes of Capitol Hill squarely focused on the Senate impeachment proceedings, we turn this w...

Read More >

Dollar General Reaches Settlement with the EEOC in Years-Long Background Check Bias Suit

Employers should continue to exercise caution and care in drafting their criminal record screening p...

Read More >

Workplace Violence Prevention In An Active-Shooter Era

Earlier this month, the country was again rocked by mass shootings—two in less than 24 hours left t...

Read More >

NLRB Restores Order to the “Dynamic Status Quo”

On August 22, 2019, a three-member panel of the National Labor Relations Board (NLRB) ruled unanimou...

Read More >