Massachusetts Court Clarifies Statute of Repose Trigger for Multi-Phase Construction Projects

In D’Allesandro v. Lennar Hingham Holdings, LLC, C.A. No. 17-cv-12567-IT, 2019 U.S. Dist. LEXIS 185874, the United States District Court for the District of Massachusetts recently discussed a case against a general contractor and its related...
By: White and Williams LLP
Source Url: https://www.jdsupra.com/legalnews/massachusetts-court-clarifies-statute-34337/

Related

Citing Trulia and Walgreens Decisions, Federal District Court Orders Plaintiffs’ Counsel to Return Agreed-Upon Mootness Fee

House v. Akorn, Inc., Consol. Nos. 17-C-5018, 17-C-5022, 17-C-5026 (N.D. Ill. Jun. 24, 2019). Discl...

Read More >

Construction Law Zone - June 2020

DRONES - Balancing New Technology and Privacy When Using Drones in Land Use and Construction - The...

Read More >

Emerging Technologies Washington Update - January 2020 #2

This Week: Senate Commerce Committee holds hearing on industries of the future, IRS launches gig eco...

Read More >

July 1, 2019 Minimum Wage Increases in California Counties and Municipalities

Many California employees received a raise on January 1, 2019 when the state increased the minimum w...

Read More >

Annual HSR Threshold Adjustments Announced for 2021

FTC adjusts the Hart-Scott-Rodino Act size thresholds, lowering the minimum size for reportable acqu...

Read More >

COVID-19: EPC and EPCM in Large Construction Projects Post COVID-19

COVID-19 has highlighted some of the existing problems in the construction market such as fragmentat...

Read More >