Massachusetts Court Clarifies Statute of Repose Trigger for Multi-Phase Construction Projects

In D’Allesandro v. Lennar Hingham Holdings, LLC, C.A. No. 17-cv-12567-IT, 2019 U.S. Dist. LEXIS 185874, the United States District Court for the District of Massachusetts recently discussed a case against a general contractor and its related...
By: White and Williams LLP
Source Url: https://www.jdsupra.com/legalnews/massachusetts-court-clarifies-statute-34337/

Related

If Pain (or Anything Else), Yes Gain—Part 73: Bernalillo County, NM Enacts First Local Paid Time Off Ordinance

Seyfarth Synopsis: Last month, Bernalillo County, NM became the first local jurisdiction to enact a ...

Read More >

DOL Finalizes New Rule That Will Potentially Make Millions of Employees Eligible For Overtime Pay In January 2020

On September 24, 2019, the U.S. Department of Labor (DOL) announced a final rule that, effective Jan...

Read More >

Supreme Court’s Epic Systems Decision On Arbitration Interpreted Broadly By Labor Board

An employer may lawfully issue to its employees a new or revised mandatory arbitration agreement con...

Read More >

Construction During a Pandemic – Pillsbury’s 50-State Survey of COVID-19 Impact on Construction Services (UPDATED)

Pillsbury continues to track the impact on construction projects of COVID-19-related orders and guid...

Read More >

Settlement of First Delaware PE Busted Deal Case on Eve of Trial

In July 2020, Quinn Emanuel achieved a favorable settlement for its client Advent International in t...

Read More >

The Board's Role in Corporate Compliance is Changing - Fast

Key Takeaways from Foley's National Directors Institute Conference Panel - When it comes to a corp...

Read More >