09Jan
Massachusetts Court Clarifies Statute of Repose Trigger for Multi-Phase Construction Projects
In D’Allesandro v. Lennar Hingham Holdings, LLC, C.A. No. 17-cv-12567-IT, 2019 U.S. Dist. LEXIS 185874, the United States District Court for the District of Massachusetts recently discussed a case against a general contractor and its related...
By:
White and Williams LLP
Source Url: https://www.jdsupra.com/legalnews/massachusetts-court-clarifies-statute-34337/
Related
Arnall Golden Gregory LLP is pleased to provide you with the Compliance News Flash, which includes c...
Read More >
The Situation: Several changes to Dutch employment law took effect January 1, 2020, most notably tho...
Read More >
On January 7, 2020, the U.S. Department of Labor published three new opinion letters – two that add...
Read More >
On Friday, August 9, 2019, the National Labor Relations Board (“NLRB” or “Board”) issued its fir...
Read More >
In this episode of Great Women in Compliance, Lisa speaks with Andrea Bonime Blanc, who has "done it...
Read More >
The COVID-19 pandemic is causing disruption to a wide range of industries and construction in the he...
Read More >