Contracting Offficer’s Belief That Contractor Could Not Meet Schedule Requirements Insufficient to Support Default Termination

Burr & Forman | | Return|
There is objection evidence.  There is subjective evidence.  And sometimes, it is a combination of both  A case cannot go much worse when a court’s opinion starts with the following: “This case concerns a contract in which a number of disputes, poor...
By: Burr & Forman
Source Url: https://www.jdsupra.com/legalnews/contracting-offficer-s-belief-that-94175/

Related

IRS Issues Final Regulations on 401(k) Hardship Distributions

The Internal Revenue Service recently published final regulations modifying the rules relating to ha...

Read More >

Deciding When a Misstatement to a Court Makes a Mockery of the Judicial System

When a litigant makes a statement to one court, and later makes a contradictory statement to another...

Read More >

Massachusetts Enacts H. 4647 – Establishing Broad Eviction and Foreclosure Moratorium During COVID-19 State of Emergency

On April 20, 2020, Massachusetts enacted a statewide moratorium on a broad swath of evictions and fo...

Read More >

NLRB: After Boeing, Union Organizing Becomes Harder

In 2011, in Specialty Healthcare & Rehabilitation Center of Mobile, an Obama-era majority of the Nat...

Read More >

Egypt Pursues Innovative Alternatives to Merger Control

Recent merger enforcement activities by the Egyptian Competition Authority ("ECA") raise warning sig...

Read More >

2020 Healthcare Authority: January 2020 #2

Digital Health Companies Look Toward IPOs as M&A Stabilizes - Digital health funding in 2019 sugges...

Read More >