Contracting Offficer’s Belief That Contractor Could Not Meet Schedule Requirements Insufficient to Support Default Termination

Burr & Forman | | Return|
There is objection evidence.  There is subjective evidence.  And sometimes, it is a combination of both  A case cannot go much worse when a court’s opinion starts with the following: “This case concerns a contract in which a number of disputes, poor...
By: Burr & Forman
Source Url: https://www.jdsupra.com/legalnews/contracting-offficer-s-belief-that-94175/

Related

Revised HSR Thresholds Released

On February 1, 2021, the Federal Trade Commission (FTC) released the revised thresholds for determin...

Read More >

The Farro Litigation: The Rest of the Story

In last week’s New York Business Divorce, Peter Mahler wrote about an important new decision with f...

Read More >

Kruse-Western Wins Partial Dismissal in ERISA Lawsuit over $244 Million Stock Sale

The federal court affirmed ERISA’s limitations on the types of claims and remedies available under ...

Read More >

Le secteur agricole et le droit de la concurrence au Canada

Le secteur agricole canadien constitue un élément important de l’économie du pays. En effet, les re...

Read More >

NYC DOB Tells Contractors How To Safely Wind Down Construction Sites

As a result of the “stop work order” on construction in New York State, many projects are now bein...

Read More >

Gun jumping: AG Tanchev tells European Court of Justice that Marine Harvest should receive one fine, not two

There has been an important milestone in the search for more legal certainty in gun-jumping cases: O...

Read More >