Contract Clause for Weather Delays Does Not Override Suspension of Work Clause
In the recent case of Granite Construction Co., ASBCA 62281, the Armed Services Board of Contract Appeals granted partial summary judgment to a contractor that sought delay damages under FAR 52.242-14, Suspension of Work—overcoming the Government's argument that the delays were contemplated under a separate clause for adverse weather delays....
By:
Davis Wright Tremaine LLP
Source Url: https://www.jdsupra.com/legalnews/contract-clause-for-weather-delays-does-4855083/
Related
On January 21, 2020, New Jersey Governor Phil Murphy signed into law three bills that increase the p...
Read More >
On October 29, 2019, The U.S. Department of Agriculture released its interim final rule for the dome...
Read More >
Join Ulmer on February 13 for a Live Webinar on What’s New in the World of ERISA - Journey to the...
Read More >
Speed read - New merger control guidelines in Indonesia provide that asset acquisitions are now tra...
Read More >
H.I.G. BioHealth Partners, the life-science investment affiliate of H.I.G. Capital, has announced th...
Read More >
In 2014, the Obama-era National Labor Relations Board made over two dozen changes to the union elect...
Read More >