Contract Clause for Weather Delays Does Not Override Suspension of Work Clause

In the recent case of Granite Construction Co., ASBCA 62281, the Armed Services Board of Contract Appeals granted partial summary judgment to a contractor that sought delay damages under FAR 52.242-14, Suspension of Work—overcoming the Government's argument that the delays were contemplated under a separate clause for adverse weather delays....
By: Davis Wright Tremaine LLP
Source Url: https://www.jdsupra.com/legalnews/contract-clause-for-weather-delays-does-4855083/

Related

Governor Newsom Pumps Brakes On New Sexual Harassment Training Requirements

Seyfarth Synopsis: California employers racing to ensure all their employees receive mandatory haras...

Read More >

The message has to resonate

For some reason, my unincorporated village doesn’t have a mayor or village board of trustees, but w...

Read More >

Chancery Court Looks Past “Sham” Paper Trail to Determine Ownership of Holding Company for Argentina Media Conglomerate

In Carlos Eduardo Lorefice Lynch, et al. v. R Angel Gonzalez Gonzalez, et al., C.A. No. 2019-0356-MT...

Read More >

New Year Brings New Opinion Letters From DOL’s Wage and Hour Division

On January 7, 2020, the U.S. Department of Labor’s Wage and Hour Division (WHD) issued three opinio...

Read More >

Disclosure of financial information in viability assessments: Considerations for developers

The recent judicial review in R (Holborn Studios) v London Borough of Hackney raises important consi...

Read More >