Contract Clause for Weather Delays Does Not Override Suspension of Work Clause

In the recent case of Granite Construction Co., ASBCA 62281, the Armed Services Board of Contract Appeals granted partial summary judgment to a contractor that sought delay damages under FAR 52.242-14, Suspension of Work—overcoming the Government's argument that the delays were contemplated under a separate clause for adverse weather delays....
By: Davis Wright Tremaine LLP
Source Url: https://www.jdsupra.com/legalnews/contract-clause-for-weather-delays-does-4855083/

Related

La proposta di revisione dell'art. 14 del D.M. 30/2015 in consultazione

Il Ministero dell’Economia e delle Finanze, Dipartimento del Tesoro (“MEF”) ha da qualche giorno ...

Read More >

[Video] Compliance into the Weeds-Episode 148, Procurement Collusion Strike Force

Compliance into the Weeds is the only weekly podcast which takes a deep dive into a compliance relat...

Read More >

M&A Watch: Seeking Your True Purpose? Delaware Offers Guidance on Section 220 Requests

Following Corwin v. KKR Financial Holdings and other Delaware cases that have reinforced the standar...

Read More >

[Event] Economic Trends and Outlook for 2020 - January 30th, San Francisco, CA

Please join us to hear remarks from Dean Ann Harrison, one of the most highly-cited scholars on mult...

Read More >

EEOC Sues Citizens Bank for Disability Bias

Company Refused to Accommodate Employee With Anxiety By Reassignment to Vacant Position, Federal Age...

Read More >

Delaware Chancery Court Holds That a Transaction Involving a Conflicted Board Majority Can Be Cleansed If Appropriate Safeguards Are Implemented

In a legal challenge to a corporate transaction, the applicable standard of review is often outcome ...

Read More >