Contract Clause for Weather Delays Does Not Override Suspension of Work Clause
In the recent case of Granite Construction Co., ASBCA 62281, the Armed Services Board of Contract Appeals granted partial summary judgment to a contractor that sought delay damages under FAR 52.242-14, Suspension of Work—overcoming the Government's argument that the delays were contemplated under a separate clause for adverse weather delays....
By:
Davis Wright Tremaine LLP
Source Url: https://www.jdsupra.com/legalnews/contract-clause-for-weather-delays-does-4855083/
Related
Seyfarth Synopsis: California employers racing to ensure all their employees receive mandatory haras...
Read More >
For some reason, my unincorporated village doesn’t have a mayor or village board of trustees, but w...
Read More >
The Federal Trade Commission (FTC) announced a new temporary suspension of grants of early terminati...
Read More >
In Carlos Eduardo Lorefice Lynch, et al. v. R Angel Gonzalez Gonzalez, et al., C.A. No. 2019-0356-MT...
Read More >
On January 7, 2020, the U.S. Department of Labor’s Wage and Hour Division (WHD) issued three opinio...
Read More >
The recent judicial review in R (Holborn Studios) v London Borough of Hackney raises important consi...
Read More >