Contract Clause for Weather Delays Does Not Override Suspension of Work Clause
In the recent case of Granite Construction Co., ASBCA 62281, the Armed Services Board of Contract Appeals granted partial summary judgment to a contractor that sought delay damages under FAR 52.242-14, Suspension of Work—overcoming the Government's argument that the delays were contemplated under a separate clause for adverse weather delays....
By:
Davis Wright Tremaine LLP
Source Url: https://www.jdsupra.com/legalnews/contract-clause-for-weather-delays-does-4855083/
Related
A number of questions have arisen concerning the impact of the recently adopted Housing Stability an...
Read More >
Many employers loathe the prospect of unionization due to the potential of a union hampering such em...
Read More >
With the uncertainty of COVID-19 impacting construction projects in new and unfamiliar ways, choosin...
Read More >
It’s no secret that many employers have employees sign arbitration agreements with class and collec...
Read More >
We include the 2018 chapter in its entirety for reference following the 2019 update. Background - ...
Read More >
OSHA recently modernized its Whistleblower Protection Program Website. The redesigned site includes ...
Read More >