Contract Clause for Weather Delays Does Not Override Suspension of Work Clause

In the recent case of Granite Construction Co., ASBCA 62281, the Armed Services Board of Contract Appeals granted partial summary judgment to a contractor that sought delay damages under FAR 52.242-14, Suspension of Work—overcoming the Government's argument that the delays were contemplated under a separate clause for adverse weather delays....
By: Davis Wright Tremaine LLP
Source Url: https://www.jdsupra.com/legalnews/contract-clause-for-weather-delays-does-4855083/

Related

Retaining Independent Contractors in New Jersey Just Got Even Riskier

On January 21, 2020, New Jersey Governor Phil Murphy signed into law three bills that increase the p...

Read More >

Construction & Real Estate E-Note - December 2019

On October 29, 2019, The U.S. Department of Agriculture released its interim final rule for the dome...

Read More >

[Webinar] What's New in the World of ERISA? - February 13th, 2:00 pm ET

Join Ulmer on February 13 for a Live Webinar on What’s New in the World of ERISA - Journey to the...

Read More >

Asset acquisitions caught by the Indonesian merger control regime

Speed read - New merger control guidelines in Indonesia provide that asset acquisitions are now tra...

Read More >

Healthcare & Life Sciences Private Equity Deal Tracker: H.I.G BioHealth Sells Vertiflex to Boston Scientific

H.I.G. BioHealth Partners, the life-science investment affiliate of H.I.G. Capital, has announced th...

Read More >

NLRB Announces New Union Election Procedures

In 2014, the Obama-era National Labor Relations Board made over two dozen changes to the union elect...

Read More >