Contract Clause for Weather Delays Does Not Override Suspension of Work Clause

In the recent case of Granite Construction Co., ASBCA 62281, the Armed Services Board of Contract Appeals granted partial summary judgment to a contractor that sought delay damages under FAR 52.242-14, Suspension of Work—overcoming the Government's argument that the delays were contemplated under a separate clause for adverse weather delays....
By: Davis Wright Tremaine LLP
Source Url: https://www.jdsupra.com/legalnews/contract-clause-for-weather-delays-does-4855083/

Related

Financial Daily Dose 9.24.2020 | Top Story: JPMorgan Nears $1B Settlement Over Alleged Spoofing

JPMorgan is preparing to finalize a deal with federal prosecutors and regulators in which the bank w...

Read More >

New York Courts Continue to Uphold Enforceability of No Damages for Delay Clauses - Construction and Procurement Law News, Q2 2019

A New York trial court recently upheld the enforceability of a no-damages-for-delay clause in a cont...

Read More >

New Final Regulations on Hardship Distributions from 401(k) and 403(b) Plans

Previous regulations on hardship distributions from 401(k) and 403(b) plans generally provided that ...

Read More >

[Video] Daily Compliance News: October 19, 2019- the Mother Said ‘Don’t Tell Lies’ edition

In today’s edition of Daily Compliance News: 1. There’s a reason Mother said don’t tell lies. (B...

Read More >

The CPSC Releases Framework of Safety for the Internet of Things

The rapidly developing technology of interconnected software allows consumers to reach new heights o...

Read More >