Contract Clause for Weather Delays Does Not Override Suspension of Work Clause

In the recent case of Granite Construction Co., ASBCA 62281, the Armed Services Board of Contract Appeals granted partial summary judgment to a contractor that sought delay damages under FAR 52.242-14, Suspension of Work—overcoming the Government's argument that the delays were contemplated under a separate clause for adverse weather delays....
By: Davis Wright Tremaine LLP
Source Url: https://www.jdsupra.com/legalnews/contract-clause-for-weather-delays-does-4855083/

Related

Considerations When Supporting and Participating in National Party Conventions

Now that the calendar has flipped to 2020, planning and fundraising efforts are intensifying in adva...

Read More >

CARES Act Questions for the Real Estate and Construction Industry - Update #8

Congress recently passed the economic stimulus package referred to as the Coronavirus Aid, Relief, a...

Read More >

The IRS Doesn’t Disappoint…Again

As imagined by plan sponsors of closed defined benefit pension plans, the IRS issued Notice 201-49, ...

Read More >

NLRB 2020 Predictor: It’s Good to be an Employer

As not just a new year but a new decade begins, we know from the closing days of 2019 that the Natio...

Read More >

CAS Legal Mailbag Question of the Week – November 2019 #2

Dear Legal Mailbag: I was appointed this fall to serve as an assistant principal at a new school. E...

Read More >

SECURE Act Impacts Estate Plans: Here’s What to Know (Part I)

A new law, which is called “SECURE” (Setting Every Community Up for Retirement Enhancement), appli...

Read More >