Contract Clause for Weather Delays Does Not Override Suspension of Work Clause
In the recent case of Granite Construction Co., ASBCA 62281, the Armed Services Board of Contract Appeals granted partial summary judgment to a contractor that sought delay damages under FAR 52.242-14, Suspension of Work—overcoming the Government's argument that the delays were contemplated under a separate clause for adverse weather delays....
By:
Davis Wright Tremaine LLP
Source Url: https://www.jdsupra.com/legalnews/contract-clause-for-weather-delays-does-4855083/
Related
Now that the calendar has flipped to 2020, planning and fundraising efforts are intensifying in adva...
Read More >
Congress recently passed the economic stimulus package referred to as the Coronavirus Aid, Relief, a...
Read More >
As imagined by plan sponsors of closed defined benefit pension plans, the IRS issued Notice 201-49, ...
Read More >
As not just a new year but a new decade begins, we know from the closing days of 2019 that the Natio...
Read More >
Dear Legal Mailbag: I was appointed this fall to serve as an assistant principal at a new school. E...
Read More >
A new law, which is called “SECURE” (Setting Every Community Up for Retirement Enhancement), appli...
Read More >