28Jan
Contract Clause for Weather Delays Does Not Override Suspension of Work Clause
In the recent case of Granite Construction Co., ASBCA 62281, the Armed Services Board of Contract Appeals granted partial summary judgment to a contractor that sought delay damages under FAR 52.242-14, Suspension of Work—overcoming the Government's argument that the delays were contemplated under a separate clause for adverse weather delays....
By:
Davis Wright Tremaine LLP
Source Url: https://www.jdsupra.com/legalnews/contract-clause-for-weather-delays-does-4855083/
Related
In the wake of the new minimum wage law passed earlier this month, eight immigrant workers have file...
Read More >
2019 Update: In 2018, PETERKA & PARTNERS drafted the following chapter on what Slovakian companies n...
Read More >
The French Data Protection Authority (CNIL) published new Guidelines (French only) on December 10, 2...
Read More >
On February 21, 2020, OFCCP launched an online training platform called the Contractor Compliance In...
Read More >
On December 19, 2019, the Rhode Island Contractors Registration and Licensing Board’s (“CRLB”) re...
Read More >
Can a breach of one contract give rise to liability for lost profit on a related contract? Or is the...
Read More >