Contract Clause for Weather Delays Does Not Override Suspension of Work Clause

In the recent case of Granite Construction Co., ASBCA 62281, the Armed Services Board of Contract Appeals granted partial summary judgment to a contractor that sought delay damages under FAR 52.242-14, Suspension of Work—overcoming the Government's argument that the delays were contemplated under a separate clause for adverse weather delays....
By: Davis Wright Tremaine LLP
Source Url: https://www.jdsupra.com/legalnews/contract-clause-for-weather-delays-does-4855083/

Related

[Video] Compliance into the Weeds: Episode 138-the Juniper Networks FCPA Enforcement Action

Compliance into the Weeds is the only weekly podcast which takes a deep dive into a compliance relat...

Read More >

San Francisco Employers May Have To Pay More In Paid Parental Leave Benefits In 2020

As Bay Area employers are well aware, San Francisco has several local employment-related ordinances ...

Read More >

Creating the Space: Healthcare Employers Implement Programs for Nursing Mothers

Women make up the majority of employees in the healthcare industry. According to the Bureau of Labor...

Read More >

New Oregon Law Complicates Retainage on Construction Projects

If you do not follow the Oregon legislature closely, you may have missed a new law, which went into ...

Read More >

IRS Issues Proposed Regs on Rehabilitation Credit

The IRS has released 26 CFR Part 1, resolving questions regarding the five-year period to claim reha...

Read More >

[Video] FCPA Compliance Report-Episode 441, Compliance Training to Influence Behavior

In this episode I visit with Matt Galvin, Vice President, Ethics & Compliance at Anheuser-Busch InBe...

Read More >