Contract Clause for Weather Delays Does Not Override Suspension of Work Clause
In the recent case of Granite Construction Co., ASBCA 62281, the Armed Services Board of Contract Appeals granted partial summary judgment to a contractor that sought delay damages under FAR 52.242-14, Suspension of Work—overcoming the Government's argument that the delays were contemplated under a separate clause for adverse weather delays....
By:
Davis Wright Tremaine LLP
Source Url: https://www.jdsupra.com/legalnews/contract-clause-for-weather-delays-does-4855083/
Related
Nieves v. Insight Building Co., LLC, C.A. No. 2019-0464-SG (Del. Ch. Aug. 4, 2020) - The Court of C...
Read More >
Most employers know that the Occupational Safety and Health Administration can assess civil penaltie...
Read More >
Private equity (PE) investment in physician groups has steadily grown over the last several years, w...
Read More >
The Federal Trade Commission and the Antitrust Division of the U.S. Department of Justice released t...
Read More >
Emotional support animals seem to be everywhere. We see them on planes, in restaurants, and other bu...
Read More >
On June 24, 2019, the U.S. Supreme Court — in a 6 to 3 decision — held that a seaman may not recov...
Read More >