Contract Clause for Weather Delays Does Not Override Suspension of Work Clause

In the recent case of Granite Construction Co., ASBCA 62281, the Armed Services Board of Contract Appeals granted partial summary judgment to a contractor that sought delay damages under FAR 52.242-14, Suspension of Work—overcoming the Government's argument that the delays were contemplated under a separate clause for adverse weather delays....
By: Davis Wright Tremaine LLP
Source Url: https://www.jdsupra.com/legalnews/contract-clause-for-weather-delays-does-4855083/

Related

EU Adopts Whistleblowing Directive to Protect Whistleblowers

The whistleblowing rules in Europe are about to change dramatically. The new Directive on the protec...

Read More >

Post-Closure Care at Hazardous Waste Units Closed with Waste in Place: U.S. EPA Office of Inspector General Project Notification

The United States Environmental Protection Agency (“EPA”) Office of Inspector General (“OIG”) is...

Read More >

Adecco USA to Pay $49,500 to Settle EEOC Disability Discrimination Suit

Staffing Agency Refused to Hire Employee Due to Disability, Federal Agency Charged - Pittsburgh - ...

Read More >

[Podcast]: California's Legislative Response to the #MeToo Movement

In this episode of The Proskauer Brief, partners Tony Oncidi and Kate Gold discuss California’s mos...

Read More >

Antitrust in focus December 2019

This newsletter is our take on the antitrust developments we think are most interesting to your busi...

Read More >

Virginia Task Force Releases Recommendations To Address Worker Misclassification

Virginia Governor Ralph Northam’s Inter-Agency Taskforce on Worker Misclassification and Payroll Fr...

Read More >