Contract Clause for Weather Delays Does Not Override Suspension of Work Clause
In the recent case of Granite Construction Co., ASBCA 62281, the Armed Services Board of Contract Appeals granted partial summary judgment to a contractor that sought delay damages under FAR 52.242-14, Suspension of Work—overcoming the Government's argument that the delays were contemplated under a separate clause for adverse weather delays....
By:
Davis Wright Tremaine LLP
Source Url: https://www.jdsupra.com/legalnews/contract-clause-for-weather-delays-does-4855083/
Related
On November 1, 2017, the Ohio Board of Building Standards (OBBS) adopted an update to the Ohio Build...
Read More >
As the holiday season approaches, it is a good time for employers to review their policies and take ...
Read More >
Part I described various strategies to help smaller and early-stage life science companies establish...
Read More >
Effective as of May 13, 2019, the U.S. Internal Revue Service (IRS) made a change to the application...
Read More >
May Colorado employers adopt “use-it-or-lose-it” vacation policies, in which employees lose paid v...
Read More >
Unless you have been living off the grid for the past year, you likely know that we are now down to ...
Read More >