Contract Clause for Weather Delays Does Not Override Suspension of Work Clause

In the recent case of Granite Construction Co., ASBCA 62281, the Armed Services Board of Contract Appeals granted partial summary judgment to a contractor that sought delay damages under FAR 52.242-14, Suspension of Work—overcoming the Government's argument that the delays were contemplated under a separate clause for adverse weather delays....
By: Davis Wright Tremaine LLP
Source Url: https://www.jdsupra.com/legalnews/contract-clause-for-weather-delays-does-4855083/

Related

Chancery Dismisses Claim for Breach of Fiduciary Duty Where Parties’ Commercial Relationship Was One of Ordinary Care

Nieves v. Insight Building Co., LLC, C.A. No. 2019-0464-SG (Del. Ch. Aug. 4, 2020) - The Court of C...

Read More >

Federal Court Sentences Business Owner to Prison for Violating Fall Protections

Most employers know that the Occupational Safety and Health Administration can assess civil penaltie...

Read More >

Cannabis Mergers Skewed Hart-Scott-Rodino Report Data

The Federal Trade Commission and the Antitrust Division of the U.S. Department of Justice released t...

Read More >

A Peacock Walks into the Office

Emotional support animals seem to be everywhere. We see them on planes, in restaurants, and other bu...

Read More >

Supreme Court Rejects Seaman’s Claim for Punitive Damages

On June 24, 2019, the U.S. Supreme Court — in a 6 to 3 decision — held that a seaman may not recov...

Read More >