Contract Clause for Weather Delays Does Not Override Suspension of Work Clause
In the recent case of Granite Construction Co., ASBCA 62281, the Armed Services Board of Contract Appeals granted partial summary judgment to a contractor that sought delay damages under FAR 52.242-14, Suspension of Work—overcoming the Government's argument that the delays were contemplated under a separate clause for adverse weather delays....
By:
Davis Wright Tremaine LLP
Source Url: https://www.jdsupra.com/legalnews/contract-clause-for-weather-delays-does-4855083/
Related
The Williams Cos., Inc. v. Energy Transfer LP, C.A. No. 12168-VCG (Del. Ch. July 2, 2020) - The Cou...
Read More >
JPMorgan is preparing to finalize a deal with federal prosecutors and regulators in which the bank w...
Read More >
A New York trial court recently upheld the enforceability of a no-damages-for-delay clause in a cont...
Read More >
Previous regulations on hardship distributions from 401(k) and 403(b) plans generally provided that ...
Read More >
In today’s edition of Daily Compliance News: 1. There’s a reason Mother said don’t tell lies. (B...
Read More >
The rapidly developing technology of interconnected software allows consumers to reach new heights o...
Read More >