Contract Clause for Weather Delays Does Not Override Suspension of Work Clause

In the recent case of Granite Construction Co., ASBCA 62281, the Armed Services Board of Contract Appeals granted partial summary judgment to a contractor that sought delay damages under FAR 52.242-14, Suspension of Work—overcoming the Government's argument that the delays were contemplated under a separate clause for adverse weather delays....
By: Davis Wright Tremaine LLP
Source Url: https://www.jdsupra.com/legalnews/contract-clause-for-weather-delays-does-4855083/

Related

Ohio Attorney General clarifies storm shelter moratorium financing requirements for public and private schools

On November 1, 2017, the Ohio Board of Building Standards (OBBS) adopted an update to the Ohio Build...

Read More >

EEOC Lawsuit Reminds Employers To Exercise Caution In Planning And Executing Holiday Parties

As the holiday season approaches, it is a good time for employers to review their policies and take ...

Read More >

Revised EIN Application Process Requires Individuals to Serve as the “Responsible Party”

Effective as of May 13, 2019, the U.S. Internal Revue Service (IRS) made a change to the application...

Read More >

No Vacation From Legal Uncertainty: Colorado's Conflicting Directions About Vacation Policies

May Colorado employers adopt “use-it-or-lose-it” vacation policies, in which employees lose paid v...

Read More >

CCPA QOTD: What are the penalties for non-compliance with the CCPA?

Unless you have been living off the grid for the past year, you likely know that we are now down to ...

Read More >