15Jan
ASBCA Holds that Anticipated Days of Adverse Weather Do Not Decrease Delay Damages
Many construction contractors working with the United States Army Corps of Engineers (USACE) have seen it happen: they experience a government-caused delay or suspension, which USACE agrees to pay for, but then USACE deducts the anticipated adverse weather days stated in the contract for the delay period from the compensable time extension. That may no longer be a defensible practice after the ASBCA’s recent decision in the Appeal of Granite Construction Company....
By:
Obermayer Rebmann Maxwell & Hippel LLP
Source Url: https://www.jdsupra.com/legalnews/asbca-holds-that-anticipated-days-of-1110814/
Related
Arnall Golden Gregory LLP is pleased to provide you with the Compliance News Flash, which includes c...
Read More >
On Tuesday, October 22, 2019, a Tennessee federal judge rejected a lawsuit brought by the U.S. Equal...
Read More >
Retailers faced a difficult financing market before COVID-19 appeared, but lockdowns have made the s...
Read More >
As peer-to-peer payment applications proliferate and on-demand technologies reach new facets of peop...
Read More >
Welcome to the October issue of Blakes Competitive Edge, a monthly publication of the Blakes Competi...
Read More >
On October 11, 2019, the United States Court of Appeals for the Second Circuit affirmed a decision b...
Read More >