15Jan
ASBCA Holds that Anticipated Days of Adverse Weather Do Not Decrease Delay Damages
Many construction contractors working with the United States Army Corps of Engineers (USACE) have seen it happen: they experience a government-caused delay or suspension, which USACE agrees to pay for, but then USACE deducts the anticipated adverse weather days stated in the contract for the delay period from the compensable time extension. That may no longer be a defensible practice after the ASBCA’s recent decision in the Appeal of Granite Construction Company....
By:
Obermayer Rebmann Maxwell & Hippel LLP
Source Url: https://www.jdsupra.com/legalnews/asbca-holds-that-anticipated-days-of-1110814/
Related
All sectors of the construction industry have faced unique challenges in 2020, but none has been mor...
Read More >
Last Friday night, President Trump signed into law a year-end $1.4 trillion spending bill that will ...
Read More >
The potency of the hashtag #MeToo may have passed its zenith, but “paradigm shift” is still entire...
Read More >
Litigation has its place, but most in-house counsel agree: avoid it if at all possible. That’s why ...
Read More >
On February 27, the Delaware Court of Chancery issued important guidance to boards of directors seek...
Read More >
Tailored considerations for boards of directors and management in the current environment. Key Poin...
Read More >