Case Law Update: Setoffs and the “Prevailing Party” Determination

Carlton Fields | | Return|
The Diaz Fritz Group Inc. was the general contractor for the construction of an addition to the University Community Hospital in Tampa, Florida. Diaz Fritz hired a subcontractor, Hayward Baker Inc., to perform foundation work on the project in exchange for $290,000. When Hayward Baker completed its work, Diaz Fritz refused to pay claiming that Hayward Baker was responsible for damage caused to the hospital’s existing building. Hayward Baker denied responsibility and filed a claim of lien in...
By: Carlton Fields
Source Url: https://www.jdsupra.com/legalnews/case-law-update-setoffs-and-the-8638178/

Related

Actualización del sector P3 nacional: educación superior e infraestructura social

En el pasado escribimos sobre cómo el modelo de entrega de proyectos de asociaciones público-privada...

Read More >

Coronavirus: Workplace Considerations Related to Global Supply Shortages and Employee Travel

The coronavirus has significantly impacted supply chains across the globe, and while companies exper...

Read More >

Massachusetts’ Reopening Plan: What Businesses in Phase 1 Need to Know

On May 18, 2020, the Baker-Polito Administration revealed its four-phased approach to reopening the ...

Read More >

Anticipated Changes to Employment-Based Green Card Processing

U.S. employers and foreign workers could soon face significant additional burdens and years-long del...

Read More >

Recess round-up - A quick reference guide to the key recent planning and development changes

It's difficult enough to keep on top of the news at the moment – not to mention the raft of recent ...

Read More >

Mandatory CFIUS Filing Requirement for Certain Foreign Investments Takes Effect TODAY; Exceptions for Canadian, Australian and U.K. Investors

Department of Treasury Issues Final FIRRMA Regulations - The U.S. Treasury Department has issued fi...

Read More >