07Jan
Case Law Update: Setoffs and the “Prevailing Party” Determination
The Diaz Fritz Group Inc. was the general contractor for the construction of an addition to the University Community Hospital in Tampa, Florida. Diaz Fritz hired a subcontractor, Hayward Baker Inc., to perform foundation work on the project in exchange for $290,000. When Hayward Baker completed its work, Diaz Fritz refused to pay claiming that Hayward Baker was responsible for damage caused to the hospital’s existing building. Hayward Baker denied responsibility and filed a claim of lien in...
By:
Carlton Fields
Source Url: https://www.jdsupra.com/legalnews/case-law-update-setoffs-and-the-8638178/
Related
On September 5, 2019, the Washington Supreme Court issued a huge win for all non-agricultural employ...
Read More >
The Internal Revenue Service has extended the due date for providing the 2019 Form 1095-C (applicabl...
Read More >
In final regulations set to take effect for 2020 Forms W-2, the IRS gives employers the option of us...
Read More >
With a constantly evolving legal landscape, colleges, universities and independent schools encounter...
Read More >
Joining a chorus of cities and states addressing concerns involving employers’ failure to properly ...
Read More >
Below is a summary of those key provisions. I. SECURE Act The Setting Every Community Up for Retirem...
Read More >