Case Law Update: Setoffs and the “Prevailing Party” Determination
The Diaz Fritz Group Inc. was the general contractor for the construction of an addition to the University Community Hospital in Tampa, Florida. Diaz Fritz hired a subcontractor, Hayward Baker Inc., to perform foundation work on the project in exchange for $290,000. When Hayward Baker completed its work, Diaz Fritz refused to pay claiming that Hayward Baker was responsible for damage caused to the hospital’s existing building. Hayward Baker denied responsibility and filed a claim of lien in...
By:
Carlton Fields
Source Url: https://www.jdsupra.com/legalnews/case-law-update-setoffs-and-the-8638178/
Related
As colleges and universities across the country deal with the challenges of remote learning and try ...
Read More >
On September 19, 2019, the Second Circuit issued a key pro-arbitration decision, which also decided ...
Read More >
The New Jersey Supreme Court just agreed to review whether the “good faith” defense is available t...
Read More >
Joining the wave of jurisdictions limiting the competitive restraints employers may place on low-wag...
Read More >
We have been getting accountability all wrong in the compliance profession. It's not a set of tasks ...
Read More >
SMALL BUSINESS PROGRAMS & ADVISORY SERVICES - General Services Administration - According to Law36...
Read More >