Case Law Update: Setoffs and the “Prevailing Party” Determination
The Diaz Fritz Group Inc. was the general contractor for the construction of an addition to the University Community Hospital in Tampa, Florida. Diaz Fritz hired a subcontractor, Hayward Baker Inc., to perform foundation work on the project in exchange for $290,000. When Hayward Baker completed its work, Diaz Fritz refused to pay claiming that Hayward Baker was responsible for damage caused to the hospital’s existing building. Hayward Baker denied responsibility and filed a claim of lien in...
By:
Carlton Fields
Source Url: https://www.jdsupra.com/legalnews/case-law-update-setoffs-and-the-8638178/
Related
As the COVID-19 crisis continues to make capital markets, including venture capital, an uncertain so...
Read More >
The Internal Revenue Service (IRS) ruled that a taxable real estate investment trust (REIT) subsidia...
Read More >
Last May OSHA began enforcing various provisions of the agency’s requirements of the beryllium stan...
Read More >
Steering board members clear of being named plan fiduciaries is a start. Most board members don’t ...
Read More >
In a 2-1 decision, the Fifth Circuit Court of Appeals has upheld a district court ruling that the in...
Read More >
After postponing the licensing of insolvency practitioners due to COVID-19, the licensing regime and...
Read More >