Case Law Update: Setoffs and the “Prevailing Party” Determination

Carlton Fields | | Return|
The Diaz Fritz Group Inc. was the general contractor for the construction of an addition to the University Community Hospital in Tampa, Florida. Diaz Fritz hired a subcontractor, Hayward Baker Inc., to perform foundation work on the project in exchange for $290,000. When Hayward Baker completed its work, Diaz Fritz refused to pay claiming that Hayward Baker was responsible for damage caused to the hospital’s existing building. Hayward Baker denied responsibility and filed a claim of lien in...
By: Carlton Fields
Source Url: https://www.jdsupra.com/legalnews/case-law-update-setoffs-and-the-8638178/

Related

Portland Exempts Construction Companies and Contractors From City’s 1% Gross Receipts Tax

Since January 1, 2019, Portland has imposed a 1% gross receipts surcharge tax on “large retailers.”...

Read More >

NLRB Takes Commonsense Approach on Work Rule Enforcement

In a recent decision, a majority of the National Labor Relations Board (NLRB) overturned an administ...

Read More >

New Jersey Expands Law Against Discrimination to Protect to Race-Based Hairstyles

On December 19, 2019, Governor Phil Murphy signed the Create a Respectful and Open Workspace for Nat...

Read More >

Not All Debts Are Created Equal - Construction and Procurement Law News, Q3 2019

Alabama’s materialman’s lien statute (specifically, Ala. Code § 35-11-211) was drafted with the in...

Read More >

2020 securities, shareholder, and M&A litigation outlook - April 2020

Our "2020 securities, shareholder, and M&A litigation outlook" provides our point of view on 2020, i...

Read More >

Implications for employers in Mexico regarding the coronavirus

Derived from recent events worldwide, in the event that the Mexican authorities issue a declaration ...

Read More >