07Jan
Case Law Update: Setoffs and the “Prevailing Party” Determination
The Diaz Fritz Group Inc. was the general contractor for the construction of an addition to the University Community Hospital in Tampa, Florida. Diaz Fritz hired a subcontractor, Hayward Baker Inc., to perform foundation work on the project in exchange for $290,000. When Hayward Baker completed its work, Diaz Fritz refused to pay claiming that Hayward Baker was responsible for damage caused to the hospital’s existing building. Hayward Baker denied responsibility and filed a claim of lien in...
By:
Carlton Fields
Source Url: https://www.jdsupra.com/legalnews/case-law-update-setoffs-and-the-8638178/
Related
Seyfarth Synopsis: The U.S. Bureau of Labor Statistics (BLS) recently released its annual National C...
Read More >
In William Lansing v. Doe, 2019 Ore. App. LEXIS 1564, the Court of Appeals of Oregon considered whet...
Read More >
Obesity has been recognized as a disease by the American Medical Association, National Institutes of...
Read More >
I came across a short court order a few days ago that admonished settling parties in an FLSA suit fo...
Read More >
What California developers need to know about permit deadlines and extensions during COVID-19 disrup...
Read More >
Under current EU merger control rules, whether a concentration has to be notified to the European Co...
Read More >