Case Law Update: Setoffs and the “Prevailing Party” Determination

Carlton Fields | | Return|
The Diaz Fritz Group Inc. was the general contractor for the construction of an addition to the University Community Hospital in Tampa, Florida. Diaz Fritz hired a subcontractor, Hayward Baker Inc., to perform foundation work on the project in exchange for $290,000. When Hayward Baker completed its work, Diaz Fritz refused to pay claiming that Hayward Baker was responsible for damage caused to the hospital’s existing building. Hayward Baker denied responsibility and filed a claim of lien in...
By: Carlton Fields
Source Url: https://www.jdsupra.com/legalnews/case-law-update-setoffs-and-the-8638178/

Related

Chancery Denies Motion to Dismiss Claim for Breach of Earn-Out When Unable to “Divine any Meaning” From Provision

Western Standard, LLC v. SourceHOV Holdings, Inc., C.A. No. 2018-0280-JRS (Del. Ch. July 24, 2019). ...

Read More >

Court Reverses Award of COBRA Penalties

The Sixth Circuit Court of Appeals reversed a district court’s decision to award statutory penaltie...

Read More >

Stop Work Orders and Construction Project Site Abandonment Series: Part 1 – Stop Work Orders

As the Novel-Coronavirus (“COVID-19”) continues to cause disruption to every aspect of society, th...

Read More >

Financial Daily Dose 9.11.2019 | Top Story: Hong Kong Stock Exchange Makes Surprise Bid for London Exchange

There’s some surprise market wheeling and dealing afoot this morning. The Hong Kong stock exchange ...

Read More >

Restaurant “Service Duties” Bill Fails to Get Veto Override; “Deal” Being Sought

A bill that would have brought the state’s tipping regulations in line with federal regulations was...

Read More >

Confidentiality Is Back In Fashion Following Labor Board Decision

The National Labor Relations Board (NLRB) has held under the National Labor Relations Act (NLRA) tha...

Read More >