Proceed at Your Own Risk: Government Entitled to Strict Compliance with Plans and Specifications

In Appeal of Watts Constructors, LLC, the Armed Services Board of Contract Appeals (the “Board”) held that a contractor was not excused from following contract plans and specifications despite the observation by government quality assurance inspectors of non-compliant electrical work during installation. This case is a reminder to contractors (including, of course, government contractors) that the owner is generally entitled to strict compliance with its plans and specifications, and that a...
By: Bradley Arant Boult Cummings LLP
Source Url: https://www.jdsupra.com/legalnews/proceed-at-your-own-risk-government-25364/

Related

M&A MAC Clauses – Implications of Coronavirus

Trends in Material Adverse Change Clauses – Implications of Coronavirus on M&A Transactions - On M...

Read More >

[Video] Trekking Through Compliance-Episode 54 – Bread and Circuses

In this episode of Trekking Through Compliance, we consider the episode Bread and Circuses which air...

Read More >

Tax Considerations for Financing and Refinancing Transactions in Turbulent Times

Volatile trading markets and economic instability may prompt taxpayers to modify, purchase, or repur...

Read More >

Data Privacy Day: 5 Ways to Help Employees Be #PrivacyAware

1. Help employees manage their individual privacy - Encourage employees to update their individual...

Read More >

In Dispute Over Timecard Rounding, California Court of Appeals Issues ‘Balanced’ Ruling

Timecard rounding is a tricky area of employment law. Employers like rounding because it streamlines...

Read More >