UPDATE: Supreme Judicial Court Holds That Each Building in Phased-Development Projects Constitutes Distinct “Improvement” for Purposes of Statute of Repose

Conn Kavanaugh | | Return|
Imagine the following. A developer consults with an architect in 2020 about a six-building condominium project. The architect promptly produces a set of plans, which are stamped by an engineer. Over the next three years, the developer secures the necessary permitting from a notoriously stingy local planning board. The developer finally breaks ground in 2024. He completes buildings 1-3 in 2026. Then a recession hits and the developer suspends construction for three years......
By: Conn Kavanaugh
Source Url: https://www.jdsupra.com/legalnews/update-supreme-judicial-court-holds-44957/

Related

Employer Name Error Doesn’t End Plaintiff’s ADEA Action

An employee’s error with regard to the name of his employer when he filed a charge of discriminatio...

Read More >

The Long-Awaited Final Overtime Rule Has Landed

Yesterday, the Department of Labor (DOL) released the final version of its long-anticipated update t...

Read More >

Maryland Enacts a Statute Prohibiting Non-Competes for Lower Wage Employees

On May 28, 2019, the Maryland Governor permitted (without signature) the Noncompete and Conflict of ...

Read More >

Can an insolvent company enforce an adjudicator’s decision? Yes - in exceptional circumstances

Are the regimes of construction adjudication and insolvency incompatible? Recent Court of Appeal aut...

Read More >

NLRB Limits Duty to Bargain Over Disciplinary Actions

A unionized employer must bargain with its employees’ union before making any unilateral changes in...

Read More >