X
22Jul

Timing Is Everything: Miller Act Notice Defect Saves Surety

The Miller Act protects subcontractors from nonpayment on federal projects by requiring prime contractors to issue payment bonds. To obtain relief under the Miller Act, a subcontractor must (1) give the prime contractor written notice of its claim within 90 days of the date it last performed work on a federal project and (2) file suit against the bond for any outstanding nonpayment within one year of the date work was last performed......
By: Bradley Arant Boult Cummings LLP
Source Url: https://www.jdsupra.com/legalnews/timing-is-everything-miller-act-notice-87494/

Related

FLSA Collective Action Defeated In One Fell Swoop By Exemption Defense: Way To Go!

I love it when the employer wins an exemption case because the deck is so often stacked against the ...

Read More >

Update on Foreign Direct Investments in Germany - The next tightening of the Foreign Direct Investment Rules is within reach on the horizon

Third reform within less than 3 years - On 30 January 2020, the German Federal Ministry for Econom...

Read More >

Study reports the obvious

A study from T. Rowe Price about 401(k) plan participants had some results that should really not sh...

Read More >

Update On Status Of Changes To Soon-To-Expire Form I-9

The I-9, Employment Eligibility Verification Form, that employers have been using since July 2017 is...

Read More >

Financial institutions M&A: Sector trends - February 2020: Stock Exchanges/Clearing Houses/Trading Venues

Financial institutions M&A sector trends: stock exchanges/clearing houses/trading venues — H2 2019 ...

Read More >

It’s better than nothing

Small employers have a tough time affording 401(k) plans, that’s a fact. 401(k) plans aren’t cheap...

Read More >