Federal Court Holds the Reasonableness of the Government’s Interpretation of Geotechnical Data is Irrelevant to Differing Site Condition Claim

United States Army Corps of Engineers v. John C. Grimberg Co., Inc., No. 2019-1608, 2020 BL 215269 (Fed. Cir. June 9, 2020) - The Court of Appeals for the Federal Circuit reversed a decision by the Armed Services Board of Contract Appeals (“Board”), which had found in favor of a contractor on a Type I differing site condition claim....
By: Pepper Hamilton LLP
Source Url: https://www.jdsupra.com/legalnews/federal-court-holds-the-reasonableness-42659/

Related

SEC Issues Final Rules on Registered Investment Company and Business Development Company Acquisition and Financial Statement Disclosure

The Securities and Exchange Commission (the “SEC”) recently adopted final rules (the “Final Rules...

Read More >

Wetland Mitigation Credits/Government Contract: Federal Appellate Court Addresses Contractor Request for Equitable Adjustment

The United States Court of Appeals (Federal Circuit) (“Appellate Court”) addressed in an August 26...

Read More >

Federal Court Preliminary Enjoins Enforcement of New California Arbitration Law AB 51

On Friday, January 31, 2020, Chief District Judge Kimberly J. Mueller of the federal District Court ...

Read More >

Ways To Correct Governmental Plan Problems

There are several tools that can be used to correct or fix governmental plan problems. First, some ...

Read More >

OSHA Inspection Numbers Increased in FY 2019

Seyfarth Synopsis: OSHA has just released the Agency’s enforcement and compliance inspection number...

Read More >

Healthy Workplace Discussions About Diversity, Part 2: Explaining the Foundations of Support for Organizational Diversity and Inclusion

Only just a few days ago, Virginians like me were marking the second anniversary of the violent clas...

Read More >