Michigan Federal Court Permits Subcontractor’s Quasi-Contractual Claims to Proceed Despite Existence of Express Contract Covering the Same Subject Matter

P.A.L. Environmental Safety Corp. v. North American Dismantling Corp. Et Al., No. 19-11630, 2020 BL 198779 (E.D. Mich. May 28, 2020) - A Michigan federal court partially granted Consumers Energy Company’s (“CEC”) motion to dismiss P.A.L. Environmental Safety Corporation’s (“PAL”) complaint alleging numerous causes of action in connection with its suit against CEC and contractor North American Dismantling Corporation (“NADC”) for outstanding payment stemming from asbestos abatement work at a...
By: Pepper Hamilton LLP
Source Url: https://www.jdsupra.com/legalnews/michigan-federal-court-permits-50522/

Related

Employers Take Note - 2020 Defense Spending Bill Includes “Ban the Box” Law

On December 20, 2019, President Trump signed into law a defense spending bill which included the Fai...

Read More >

Significant Changes to Dutch Employment Law Take Effect

The Situation: Several changes to Dutch employment law took effect January 1, 2020, most notably tho...

Read More >

California Supreme Court Agrees to Hear Dynamex Retroactivity Question

On November 20, 2019, the Supreme Court of California announced it would review and decide whether i...

Read More >

New NLRB Memo Addresses Social Media and Cell Phone Policies

Following its Boeing Company decision, the National Labor Relations Board continues to issue advisor...

Read More >

Beware of springboard lawyers

Hiring new lawyers is an essential part of a growing legal practice. If a legal practice is growing,...

Read More >

France hopes for recovery after COVID deal dip

French M&A activity has suffered steep falls because of COVID-19, but green shoots are emerging as l...

Read More >