Michigan Federal Court Permits Subcontractor’s Quasi-Contractual Claims to Proceed Despite Existence of Express Contract Covering the Same Subject Matter
P.A.L. Environmental Safety Corp. v. North American Dismantling Corp. Et Al., No. 19-11630, 2020 BL 198779 (E.D. Mich. May 28, 2020) - A Michigan federal court partially granted Consumers Energy Company’s (“CEC”) motion to dismiss P.A.L. Environmental Safety Corporation’s (“PAL”) complaint alleging numerous causes of action in connection with its suit against CEC and contractor North American Dismantling Corporation (“NADC”) for outstanding payment stemming from asbestos abatement work at a...
By:
Pepper Hamilton LLP
Source Url: https://www.jdsupra.com/legalnews/michigan-federal-court-permits-50522/
Related
Bricker & Eckler's construction attorneys are proud to present "Top Gun," our premier Midwest constr...
Read More >
On July 18th President Trump announced his intention to nominate Eugene Scalia to replace former Sec...
Read More >
In an effort to prevent persons with criminal records from being automatically ruled out for job vac...
Read More >
Conducting business in the Virgin Islands poses unique challenges not often encountered in the state...
Read More >
Control over pre-packs looks set to tighten further - As we stand looking into the abyss of another...
Read More >
This article is an update to prior publications from Littler’s Workplace Policy Institute regarding...
Read More >