New York Court Holds Contractor’s Failure to Timely Pass Through Subcontractor Delay Claim to the Owner Constitutes Breach of the Covenant of Good Faith and Fair Dealing

Rad and D’Aprile, Inc. v. Arnell Construction Corp, No. 502464/14, 2019 BL 131606 (NY. Sup. Ct. April 3, 2019) - In June of 2001, Arnell Construction Corp. (“Arnell”) entered into a prime contract to build two sanitation garages in Brooklyn for the...
By: Pepper Hamilton LLP
Source Url: https://www.jdsupra.com/legalnews/new-york-court-holds-contractor-s-29389/

Related

Anthem/Cigna Litigation Underscores Importance of Antitrust Planning in Transactions

On August 31, 2020, the Delaware Chancery Court issued an opinion in litigation between Anthem and C...

Read More >

Tech M&A Leaders' Survey - October 2019

The Tech M&A Leaders’ Survey is a joint effort by Morrison & Foerster and 451 Research to take the ...

Read More >

Ninth Circuit Issues A Second En Banc Decision Regarding Prior Salary Considerations In Rizo v. Yovino Re-Do

In yet another development in the closely watched case of Rizo v. Yovino, the en banc Ninth Circuit ...

Read More >

National and State Trade Groups Sue to Strike Down California “Anti-Arbitration” Law

On Friday, December 6, 2019, a coalition of national and state trade associations filed suit in Cali...

Read More >

Local Law 196 Goes Into Effect On December 1st – WHAT YOU NEED TO KNOW

Local Law 196, mandating minimum safety training requirements for workers on construction sites in N...

Read More >

Happy New Year, Employers! From Your Friends at the NLRB.

In December, the National Labor Relations Board (NLRB) issued a flurry of employer-friendly decision...

Read More >