New York Court Holds Contractor’s Failure to Timely Pass Through Subcontractor Delay Claim to the Owner Constitutes Breach of the Covenant of Good Faith and Fair Dealing

Rad and D’Aprile, Inc. v. Arnell Construction Corp, No. 502464/14, 2019 BL 131606 (NY. Sup. Ct. April 3, 2019) - In June of 2001, Arnell Construction Corp. (“Arnell”) entered into a prime contract to build two sanitation garages in Brooklyn for the...
By: Pepper Hamilton LLP
Source Url: https://www.jdsupra.com/legalnews/new-york-court-holds-contractor-s-29389/

Related

Foreign direct investment reviews 2019: A global perspective: Canada

While few deals are challenged in Canada, national security reviews are becoming more common and com...

Read More >

ARB Affirms Dismissal of SOX Whistleblower Claim Against Non-Public Companies

The ARB recently affirmed the dismissal of a whistleblower retaliation claim under Section 806 of SO...

Read More >

Antitrust M&A Snapshot - November 2019

United States: July - September 2019 Update - The Federal Trade Commission (FTC) and Department of...

Read More >

The one article I won’t write

I write a ton of articles as you may know and I will have advisors contacting me and suggesting some...

Read More >

Case of the Big Bus Driver: Seventh Circuit Joins Other Circuits in Rejecting Obesity, without Other Physiological Condition, as ADA Impairment

Obesity has been recognized as a disease by the American Medical Association, National Institutes of...

Read More >

NZ$3 billion for construction: is it enough to keep everyone working?

There were some significant announcements for the construction sector in Budget 2020: NZ$3 billion i...

Read More >