New York Court Holds Contractor’s Failure to Timely Pass Through Subcontractor Delay Claim to the Owner Constitutes Breach of the Covenant of Good Faith and Fair Dealing

Rad and D’Aprile, Inc. v. Arnell Construction Corp, No. 502464/14, 2019 BL 131606 (NY. Sup. Ct. April 3, 2019) - In June of 2001, Arnell Construction Corp. (“Arnell”) entered into a prime contract to build two sanitation garages in Brooklyn for the...
By: Pepper Hamilton LLP
Source Url: https://www.jdsupra.com/legalnews/new-york-court-holds-contractor-s-29389/

Related

“Standard” Versus “Bespoke” Boilerplate—A Distinction That Can Make a Big Difference

It keeps on happening. Contracting parties allow “standard” boilerplate to potentially trump bespo...

Read More >

Purdue Pharma, Pills, and Pot: The Need for Insurers to Have a Plan

Every day in the United States, 130 people die from opioid overdoses. To date, the opioid epidemic, ...

Read More >

Coronavirus & Material Adverse Change Clauses in M&A Deals

The coronavirus (COVID-19) global pandemic continues to dominate worldwide news cycles, and will lik...

Read More >

U.S. Department of Labor Targets Forced Labor in Fashion Industry

The U.S. Department of Labor (“DOL”) has allocated $22 million to target the growing issue of abus...

Read More >

UK Employment Flash - August 2019

In this issue of UK Employment Flash, we examine the latest employment law developments, news and in...

Read More >