The 4th Circuit Stays Construction of the Mountain Valley Pipeline — A Lesson in Preventing a Fait Accompli
Earlier this week, the 4th Circuit Court of Appeals stayed construction of the Mountain Valley Pipeline. The Court did so with a two-sentence order stating that an opinion would follow. The order was issued hours after oral argument. Why the hurry?...
By:
Foley Hoag LLP - Environmental Law
Source Url: https://www.jdsupra.com/legalnews/the-4th-circuit-stays-construction-of-52589/
Related
California Assembly Bill 5 (AB-5), a law aimed at classifying most workers as employees rather than ...
Read More >
Raising money is hard. Many founders think that it’ll be easy, and that a dozen investors will be l...
Read More >
COVID-19 has spread rapidly across the world since it first emerged in late 2019 and has impacted ev...
Read More >
Thanks to a new law just signed into effect by Governor Phil Murphy, New Jersey employers will soon ...
Read More >
One effect of the COVID-19 pandemic is the renewed need for transportation providers to consider str...
Read More >
On May 28, 2019, Colorado governor Jared Polis signed into law the Colorado Chance to Compete Act (H...
Read More >