I-30 Widening – Reconstruction/National Environmental Policy Act: U.S. District Court (E.D. Arkansas) Addresses Request For Preliminary/Permanent Injunction

United States District Judge James M. Moody (“Court”) addressed in a September 3rd Order a July 10th Motion filed by Plaintiffs seeking a preliminary and permanent injunction (“Motion”) to prohibit commencement of: . . . any construction on any portion of the proposed reconstruction of a 7.3 mile section of Interstate 30 in Little Rock and North Little Rock, Arkansas, more particularly described herein, pending a final hearing for a permanent injunction based on the merits of the First Amended...
By: Mitchell, Williams, Selig, Gates & Woodyard,
Source Url: https://www.jdsupra.com/legalnews/i-30-widening-reconstruction-national-22805/

Related

Alert: Review of EU Competition Rules on Vertical Agreements

European Commission publishes findings of its evaluation of EU competition rules on vertical agreeme...

Read More >

Failure to Specifically Challenge “Delegation” Clause in Arbitration Agreement Means Motion to Compel Arbitration “Must Be Granted”

The plaintiff sued his former employer for discrimination, retaliation, hostile work environment, an...

Read More >

The CPSC Releases Framework of Safety for the Internet of Things

The rapidly developing technology of interconnected software allows consumers to reach new heights o...

Read More >

How Internet Databases Fit Into Employer Requirements With Fair Credit Reporting Act

Most employers are aware that in order to conduct a third-party background search on an employee or ...

Read More >

Connecting data centres: attracting investors

With the explosive growth in connected working and living, data centres are attracting an increasing...

Read More >