23Jun
Michigan Federal Court Permits Subcontractor’s Quasi-Contractual Claims to Proceed Despite Existence of Express Contract Covering the Same Subject Matter
P.A.L. Environmental Safety Corp. v. North American Dismantling Corp. Et Al., No. 19-11630, 2020 BL 198779 (E.D. Mich. May 28, 2020) - A Michigan federal court partially granted Consumers Energy Company’s (“CEC”) motion to dismiss P.A.L. Environmental Safety Corporation’s (“PAL”) complaint alleging numerous causes of action in connection with its suit against CEC and contractor North American Dismantling Corporation (“NADC”) for outstanding payment stemming from asbestos abatement work at a...
By:
Pepper Hamilton LLP
Source Url: https://www.jdsupra.com/legalnews/michigan-federal-court-permits-50522/
Related
The United States Supreme Court recently denied petitions to consider two U.S. Court of Appeals deci...
Read More >
The U.S. District Court for the Western District of Wisconsin recently addressed an employer's respo...
Read More >
There have been an increasing number of reports that Immigration and Customs Enforcement (ICE) has b...
Read More >
Our December 2019 update outlines the key UK employment law developments over the last month. It inc...
Read More >
The U.S. Court of Appeals for the Eighth Circuit will soon be deciding a case that may have importan...
Read More >
A recent judgment by the Hadera Magistrate’s Court upends the common view currently reflected in ag...
Read More >