Federal Court in PA Finds Liquidated Damages Provision Unenforceable Where the Per Day Liquidated Damage Amount Was Copied from Contracts for Prior Unrelated Projects Rather than a Project-Specific Forecast of Likely Damages
D.A. Nolt, Inc. v. The Philadelphia Municipal Authority, 2020 BL 199761 (E.D. Pa. May 28, 2020) - The Philadelphia Municipal Authority (the “Authority”) contracted D.A. Nolt, Inc. (“Nolt”) to renovate a building that would serve as the City’s new...
By:
Pepper Hamilton LLP
Source Url: https://www.jdsupra.com/legalnews/federal-court-in-pa-finds-liquidated-83972/
Related
I always believe that appearances are extremely important and if things just don’t look right, they...
Read More >
President Trump signed into law the Foreign Investment Risk Review Modernization Act of 2018 (“FIRR...
Read More >
Employers who seek to sponsor foreign workers for cap-subject H-1B visas in 2020 will likely see a b...
Read More >
Female Employee Physically and Verbally Harassed By Supervisors, Federal Agency Charged - DALLAS - ...
Read More >
The Paycheck Protection Program (the “PPP”) created under the CARES Act has provided much needed a...
Read More >
Activist investor Third Point LLC and three funds that it controls have agreed to settle Federal Tra...
Read More >