Federal Court in PA Finds Liquidated Damages Provision Unenforceable Where the Per Day Liquidated Damage Amount Was Copied from Contracts for Prior Unrelated Projects Rather than a Project-Specific Forecast of Likely Damages
D.A. Nolt, Inc. v. The Philadelphia Municipal Authority, 2020 BL 199761 (E.D. Pa. May 28, 2020) - The Philadelphia Municipal Authority (the “Authority”) contracted D.A. Nolt, Inc. (“Nolt”) to renovate a building that would serve as the City’s new...
By:
Pepper Hamilton LLP
Source Url: https://www.jdsupra.com/legalnews/federal-court-in-pa-finds-liquidated-83972/
Related
When forming a construction contract, owners and developers are working to create an agreement that ...
Read More >
Seyfarth Synopsis: As they have each year since 2016, the minimum wage and exempt salary threshold w...
Read More >
In a case that should grab the attention of franchisors across the country, a panel of the US Court ...
Read More >
The U.S. Department of Transportation Office of Drug and Alcohol Policy Compliance published a notic...
Read More >
New York employers – New York State has gifted you an early holiday present – a requirement to upd...
Read More >
Corporate, social and responsibility (CSR): three words when spoken together ought to mean something...
Read More >