Federal Court in PA Finds Liquidated Damages Provision Unenforceable Where the Per Day Liquidated Damage Amount Was Copied from Contracts for Prior Unrelated Projects Rather than a Project-Specific Forecast of Likely Damages

D.A. Nolt, Inc. v. The Philadelphia Municipal Authority, 2020 BL 199761 (E.D. Pa. May 28, 2020) - The Philadelphia Municipal Authority (the “Authority”) contracted D.A. Nolt, Inc. (“Nolt”) to renovate a building that would serve as the City’s new...
By: Pepper Hamilton LLP
Source Url: https://www.jdsupra.com/legalnews/federal-court-in-pa-finds-liquidated-83972/

Related

COVID-19 Update for Energy and Infrastructure Companies and Projects

The new coronavirus (“COVID-19”) pandemic has now impacted nearly every business across the world,...

Read More >

Antitrust Alert: Eighth Circuit Upholds Injunction Against Physician Group Acquisition

In a decision that extends the FTC's winning streak in the courts of appeals in healthcare provider ...

Read More >

Tis the Season: NLRB Reverses Multiple Obama Board Decisions

Tis the season to be jolly, and the National Labor Relations Board (“NLRB” or “Board”) was in an...

Read More >

Filing Affidavit of Non-Payment Within 60 Days of Signing Statutory Lien Waiver is Critical in Georgia Construction Contracts

This fall the Georgia Court of Appeals ruled against a subcontractor who failed to file an affidavit...

Read More >

New York State Approves Broadly Expanded Protections for Employees and Applicants

New York State is on its way to enacting comprehensive reforms to broaden the scope of its discrimin...

Read More >

Annual Limits on Qualified Plans for 2020

On November 6, 2019, the Internal Revenue Service (IRS) released Notice 2019-59, which sets forth th...

Read More >