Federal Court in PA Finds Liquidated Damages Provision Unenforceable Where the Per Day Liquidated Damage Amount Was Copied from Contracts for Prior Unrelated Projects Rather than a Project-Specific Forecast of Likely Damages

D.A. Nolt, Inc. v. The Philadelphia Municipal Authority, 2020 BL 199761 (E.D. Pa. May 28, 2020) - The Philadelphia Municipal Authority (the “Authority”) contracted D.A. Nolt, Inc. (“Nolt”) to renovate a building that would serve as the City’s new...
By: Pepper Hamilton LLP
Source Url: https://www.jdsupra.com/legalnews/federal-court-in-pa-finds-liquidated-83972/

Related

A Contractor’s Guide During the Coronavirus Pandemic 2.0

The coronavirus pandemic has created novel burdens for contractors throughout the world. Project sto...

Read More >

[Webinar] The New Restrictive World of Business Immigration: Strategies to Hire and Maintain Foreign Talent - January 14th, 2:00 PM ET

Join Ulmer for a live webinar on January 14 at 2 p.m. (ET) as Partner David W. Leopold discusses wha...

Read More >

Littler Global Guide - Germany - Q2 2019

Remuneration of Business-Related Travel Time in Germany - Precedential Decision by Judiciary or Reg...

Read More >

Dear YouDig? How to avoid a design-build debacle

Dear YouDig?, We are a design builder. We hired a design team to do the preliminary design for our ...

Read More >

Financial Daily Dose 10.20.2020 | Top Story: Intel Sells Flash Memory Unit to SKY Hynix for $9 billion

Intel Corp. has reached a nearly $9 billion deal to sell its NAND flash memory unit to South Korea’...

Read More >

Pensions: What's New This Week 15 July 2019

Welcome to your weekly update from the Allen & Overy Pensions team, bringing you up to spee?d on the...

Read More >