Federal Court in PA Finds Liquidated Damages Provision Unenforceable Where the Per Day Liquidated Damage Amount Was Copied from Contracts for Prior Unrelated Projects Rather than a Project-Specific Forecast of Likely Damages

D.A. Nolt, Inc. v. The Philadelphia Municipal Authority, 2020 BL 199761 (E.D. Pa. May 28, 2020) - The Philadelphia Municipal Authority (the “Authority”) contracted D.A. Nolt, Inc. (“Nolt”) to renovate a building that would serve as the City’s new...
By: Pepper Hamilton LLP
Source Url: https://www.jdsupra.com/legalnews/federal-court-in-pa-finds-liquidated-83972/

Related

What Source Selection Method Will Create ‘Best Value’ for Your Construction Project?

When forming a construction contract, owners and developers are working to create an agreement that ...

Read More >

New York Minimum Wage and Salary Threshold for Exempt Employees Set to Increase

Seyfarth Synopsis: As they have each year since 2016, the minimum wage and exempt salary threshold w...

Read More >

Lovin' It: Ninth Circuit Rules McDonald's is Not a Joint Employer with Franchisee in California

In a case that should grab the attention of franchisors across the country, a panel of the US Court ...

Read More >

U.S. DOT Issues Warning Regarding Use Of CBD Products By DOT-Regulated Employees

The U.S. Department of Transportation Office of Drug and Alcohol Policy Compliance published a notic...

Read More >

New NY Reproductive Health Law (the “Boss Law”) Requires Immediate Action; Employers Must Update Employee Handbooks by January 7, 2020

New York employers – New York State has gifted you an early holiday present – a requirement to upd...

Read More >

An interventionist society will use negligence to hold companies to account

Corporate, social and responsibility (CSR): three words when spoken together ought to mean something...

Read More >