Federal Court in PA Finds Liquidated Damages Provision Unenforceable Where the Per Day Liquidated Damage Amount Was Copied from Contracts for Prior Unrelated Projects Rather than a Project-Specific Forecast of Likely Damages
D.A. Nolt, Inc. v. The Philadelphia Municipal Authority, 2020 BL 199761 (E.D. Pa. May 28, 2020) - The Philadelphia Municipal Authority (the “Authority”) contracted D.A. Nolt, Inc. (“Nolt”) to renovate a building that would serve as the City’s new...
By:
Pepper Hamilton LLP
Source Url: https://www.jdsupra.com/legalnews/federal-court-in-pa-finds-liquidated-83972/
Related
The coronavirus pandemic has created novel burdens for contractors throughout the world. Project sto...
Read More >
Join Ulmer for a live webinar on January 14 at 2 p.m. (ET) as Partner David W. Leopold discusses wha...
Read More >
Remuneration of Business-Related Travel Time in Germany - Precedential Decision by Judiciary or Reg...
Read More >
Dear YouDig?, We are a design builder. We hired a design team to do the preliminary design for our ...
Read More >
Intel Corp. has reached a nearly $9 billion deal to sell its NAND flash memory unit to South Korea’...
Read More >
Welcome to your weekly update from the Allen & Overy Pensions team, bringing you up to spee?d on the...
Read More >