Federal Court in PA Finds Liquidated Damages Provision Unenforceable Where the Per Day Liquidated Damage Amount Was Copied from Contracts for Prior Unrelated Projects Rather than a Project-Specific Forecast of Likely Damages

D.A. Nolt, Inc. v. The Philadelphia Municipal Authority, 2020 BL 199761 (E.D. Pa. May 28, 2020) - The Philadelphia Municipal Authority (the “Authority”) contracted D.A. Nolt, Inc. (“Nolt”) to renovate a building that would serve as the City’s new...
By: Pepper Hamilton LLP
Source Url: https://www.jdsupra.com/legalnews/federal-court-in-pa-finds-liquidated-83972/

Related

Aviation M&A braces for impact

COVID-19 travel restrictions have put the aviation industry on the backfoot. M&A will not be an imme...

Read More >

ODOT Enforcement Of Social Distancing On Projects

On April 1, 2020, ODOT provided direction on enforcement of COVID-19 social distancing on ODOT proje...

Read More >

Biden Leaves in Place Key Portions of Buy American Act Changes, Targets New Domestic End Product Test and Services

President Joe Biden issued on January 25 an Executive Order on Ensuring the Future Is Made in All of...

Read More >

COVID-19: UK Coronavirus Act 2020 - Implications for the Construction Industry

The 359-page emergency Coronavirus Bill received royal assent on 25 March 2020. This newly passed Co...

Read More >

HHS Proposed Regulations Remove Protections from the Affordable Care Act for Transgender Patients

On May 24, 2019, the U.S. Department of Health and Human Services (HHS) issued new proposed regulati...

Read More >

Back to Business: Land Use Matters & Public Hearings in Virginia

While the impact of the COVID-19 pandemic on the real estate development industry remains unclear, s...

Read More >