Practical completion: Court of Appeal provides general guidance

A clause stating that a reduction in room size by more than 3% would be “deemed material” related only to the materiality of the variation from the contract drawings, rather than the materiality of the resulting breach of contract. Parties can agree...
By: Allen & Overy LLP
Source Url: https://www.jdsupra.com/legalnews/practical-completion-court-of-appeal-25547/

Related

Identify the Four Tracks of Personal Responsibility

The divisions in this country are not just political, they also relate to attitudes toward responsib...

Read More >

OSHA Raises Fines for 2020

The Occupational Safety and Health Administration has raised its civil penalties for the fifth year ...

Read More >

Baseball Moves Forward and the Advancement of Compliance Through ComTech

What have been some of the advancements in compliance this century? One of the key recent innovation...

Read More >

COVID-19 Construction Alert: Force Majeure and Notice Provisions in Construction Contracts Take Center Stage in the Age of COVID-19

Before the advent of COVID-19, nobody paid much attention to force majeure clauses in construction c...

Read More >